Revenue Recognition
|
3 Months Ended |
---|---|
Jun. 30, 2011
|
|
Revenue Recognition [Abstract] | |
REVENUE RECOGNITION |
NOTE 3 — REVENUE RECOGNITION:
The Company recognizes revenue on all contracts with a planned manufacturing process in excess
of four weeks (which approximates 575 direct labor hours) using the percentage-of-completion
method. The majority of the Company’s revenue is recognized under this methodology. The
percentage-of-completion method is determined by comparing actual labor incurred to a specific date
to management’s estimate of the total labor to be incurred on each contract. Contracts in progress
are reviewed monthly, and sales and earnings are adjusted in current accounting periods based on
revisions in the contract value and estimated costs at completion. Losses on contracts are
recognized immediately when evident. There is no reserve for credit losses related to unbilled
revenue recorded for contracts accounted for on the percentage of completion method. Any reserve
for credit losses related to unbilled revenue is recorded as a reduction to revenue.
Revenue on contracts not accounted for using the percentage-of-completion method is recognized
utilizing the completed contract method. The majority of the Company’s contracts have a planned
manufacturing process of less than four weeks and the results reported under this method do not
vary materially from the percentage-of-completion method. The Company recognizes revenue and all
related costs on these contracts upon substantial completion or shipment to the customer.
Substantial completion is consistently defined as at least 95% complete with regard to direct labor
hours. Customer acceptance is generally required throughout the construction process and the
Company has no further material obligations under its contracts after the revenue is recognized.
|